We have been granted a 15-year lease on the building, but it is in a run-down state and requires a lot of renovation work to restore it. The renovation of the Imperial Cinema includes major structural alterations and refurbishment to convert the cinema into a suitable church venue.
Our current estimated project cost is $58M. These include:
1. Demolition of the lower part of the balcony 2. Removal of the projection room
3. Provision of a disabled/fireman lift
4. Construction of a new auditorium floor
5. Renovation of the existing two smaller cinemas into ministry rooms
6. 2 Years' operations & rental costs
BUDGET UPDATE // At the start of the project we estimated the project cost of HKD$50 million, but due to a number of factors including more structural reinforcement required than originally estimated, the total cost has risen to HKD$58 million.
| DEMOLITION & STRUCTURAL |
// |
8.09M |
| MECHANICAL & ENGINEERING |
// |
11.76M |
| EXTERNAL TREATMENT |
// |
3.08M |
| BUILDERS WORK |
// |
8.61M |
| FURNITURE & EQUIPMENT |
// |
2.00M |
| AV SOUND & LIGHTING |
// |
4.88M |
| PRELIMS |
// |
3.21M |
| CONSULTANTS FEES |
// |
5.71M |
| CONTINGENCIES |
// |
2.66M |
| FIRST 3 YEARS RENTAL |
// |
8.00M |
|
|
|
| TOTAL |
// |
58.0M |
Despite the increase in budget, the elders and senior pastors remain committed to God’s call for us to move to Wan Chai and are confident that God will continue to faithfully provide.
*All prices are in HKD. Please note that these costs are approximate estimates and not exact figures, and therefore may increase or decrease slightly.
|